Planned maintenance of VMware virtual network switch (Stockholm)

Thursday, 15 August 1 hour
Complete
Complete

The scheduled maintenance has been completed.

Underway

Scheduled maintenance is currently in progress. We will provide updates as necessary.

Scheduled

We will be performing an update of a VMware virtual switch in our Stockholm datacenter.

During this maintenance window, the uplinks of the virtual switch will be reset, which may cause some minor network disruption for a very short period of time (up to 1 min) for virtual machines running in Stockholm.

The maintenance is scheduled to take place on Thursday 15th August, 2019 between 04:00-05:00 CEST.

Began at: